The dining room can be beautiful on paper. If there is no workable route for the kitchen exhaust, the restaurant still has a problem.
Restaurant construction costs follow the menu, equipment and existing building. Set those three together before pricing the finishes. A former restaurant may offer useful infrastructure, but its systems still need assessment for the next operator.
Start with the menu and equipment schedule
List cooking equipment, refrigeration, preparation, dishwashing, storage and service stations. Identify fuel, electrical and water requirements with suppliers. A change from light preparation to intensive cooking can affect ventilation, utilities and the entire kitchen layout.
Map deliveries, food preparation, plating, dish return and waste. The customer route and staff workflow should work together without competing for the same corridor.
The cost categories that matter
Kitchen infrastructure: exhaust, make-up air, duct routes, roof work and required fire-suppression coordination.
Plumbing: sinks, hot water, drains, grease management and slab reinstatement.
Electrical and gas: available capacity, distribution, equipment connections and any service upgrades.
Refrigeration: equipment supply, installation, heat rejection, access and maintenance clearance.
Guest areas: seating layout, bar, lighting, acoustic treatments, finishes and millwork.
Support areas: washrooms, staff facilities, storage, IT, security and waste handling.
Project costs: design, permits, inspections, protection, contingency and opening supplies outside the contract.
Split equipment supply from installation and connections. An owner-purchased appliance is not a complete installed allowance. Confirm delivery access before the equipment arrives.
How much should you allow?
There is no reliable single rate without a defined restaurant and site. A café with limited preparation, a full-service kitchen and a high-specification dining room have different cost drivers. Ask for a dated estimate by trade with quantities, assumptions and exclusions.
Compare three options where relevant: reuse approved existing infrastructure, selectively upgrade it, or replace it. A lower-rent unit can be more expensive overall if the required service and exhaust work is extensive.
Read the leasehold improvements guide for landlord allowances and cash timing, and the construction-budget guide for owner costs outside the fit-out contract.
Exhaust and make-up air belong in due diligence
Have mechanical consultants determine the system requirements for the equipment and cooking process. Confirm the route through or above the building, landlord permissions, roof interfaces, maintenance access and the impact on neighbours or shared premises.
Do not assume an existing hood can serve a new menu. Check equipment compatibility, condition and the required approvals before treating reuse as a saving.
Coordinate Toronto’s approval routes
Toronto Public Health’s food-business guidance requires notification before operating and recommends checking the relevant zoning and building requirements early.
The City’s plan-submission guidance calls for equipment, sinks, food storage, waste areas and staff facilities to be identified. Coordinate public-health review with building, mechanical and plumbing permits; neither process replaces the other.
Also verify applicable business licensing, signage and any alcohol-service approvals with the relevant authorities. Their timelines belong in the opening programme.
Grease management is a design decision
Toronto’s grease-interceptor guidance explains installation obligations and states that a building permit is needed to install or replace an interceptor. Have the designer confirm sizing, connections and access. Leave room for servicing; hiding equipment where it cannot be maintained creates an operating problem.
FCC example: Mantra by Host
At Mantra by Host in North York’s Shops at Don Mills, FCC’s published scope brings together dining areas, a feature bar, commercial kitchen, support spaces and specialty finishes.
The useful lesson is coordination: the guest-facing design and working kitchen are one project. Lighting, ceilings, services and finishes need agreed interfaces. The public case study supplies project scope and photographs, not a construction-price benchmark or a verified operating-profit result.
Build the opening schedule backwards
Operator readiness, staff training and required opening inspections.
Equipment testing, cleaning, commissioning and deficiencies.
Final finishes and equipment installation.
Building-services rough-ins and required inspections.
Permits, design approvals and long-lead procurement.
Allow time for the operator’s equipment and approvals as well as construction. An opening announcement should follow a reviewed programme, not substitute for one.
Is taking over a former restaurant always cheaper?
No. Reuse helps only where the existing condition, capacity and approvals suit the proposed operation.
Who buys the kitchen equipment?
Either arrangement can work. Define procurement, delivery, installation, connections, warranties and testing in the scope before ordering.
Check the unit before the lease becomes a constraint
Send FCC the address, menu concept, equipment list and available plans. Our Interior Fit-Outs & Tenant Improvements team can help turn those inputs into a coordinated scope. Discuss your restaurant build-out.
Prepared November 18, 2026. Deep Toor, Director of Operations, FCC Builders Canada. General project-planning guidance; confirm site-specific requirements with your consultants and authorities.