The project has a loan commitment. The contractor has submitted an invoice. Why is the money not in the account yet?
Construction funding is usually advanced through an agreed process as work progresses. A loan commitment, a payment application and an approved advance are different things. Plan the time and cash between them before mobilizing.
Agree on the draw process before work starts
Ask the lender for its specific requirements: reporting dates, eligible costs, equity contributions, site reviews, legal conditions and who authorizes each release. There is no universal commercial draw schedule that fits every Ontario project.
The RICS/CIQS Canadian project-monitoring guidance describes preliminary and progress reviews for real-estate lending. It is a professional practice reference, published in 2016, rather than your lender’s current commitment or current Ontario legal advice.
How a progress draw typically moves
Record the work: the construction team assembles the payment application and supporting progress information.
Review the scope and value: designated reviewers assess completed work, changes and relevant supporting documents.
Update the forecast: report costs incurred, remaining commitments, expected changes and contingency.
Meet funding conditions: the borrower and advisers address the lender’s documentation, equity, insurance and legal requirements.
Release and reconcile: record the advance actually received and reconcile it with payments due.
The people, sequence and timing depend on the contract and lending arrangement. Agree on a calendar with document cut-offs and realistic review time.
Prepare a consistent monthly package
An updated construction budget using the same cost codes each month.
Contract commitments, approved changes and pending changes identified separately.
Payment applications, invoices and any requested declarations or payment records.
A progress summary with dated photographs and programme updates.
A cost-to-complete forecast with an explained contingency balance.
Permit, inspection, insurance and other documents requested by the lender.
Label the reporting date. Mixing last month’s schedule with this month’s costs makes a package harder to review. Assign one person to reconcile the versions before submission.
Cost to complete is more than unpaid invoices
The forecast should capture work still needed to finish the agreed project, including uncommitted work, known changes, unresolved risks and closeout. A budget that ignores a pending service upgrade can appear healthy until the purchase order arrives.
Illustrative example: a project has $1.2 million of forecast remaining cost and $1 million of confirmed remaining funding. The $200,000 gap needs a documented solution; a healthy percentage-complete figure does not close it. This is a teaching example, not an FCC project or a lender’s calculation method.
Ask the monitor and lender how they treat deposits, stored materials, taxes, owner costs, interest reserves and contingencies. An approved purchase is not necessarily immediately eligible for reimbursement.
Separate three kinds of inspection
Municipal inspection: checks work against applicable permit and code requirements within the authority’s role.
Consultant review: addresses the design and contract responsibilities of the appointed professionals.
Lender monitoring: supports the lender’s assessment of progress, costs and remaining exposure under its engagement.
One does not replace the others. A lender advance is not a certificate that every defect is resolved or every contractual payment obligation has been satisfied.
Budget for holdbacks and current Ontario rules
Section 22 of Ontario’s Construction Act generally requires a basic holdback of 10% of the value of supplied services or materials where a lien may arise. Holdback is different from a contingency or a lender’s separate reserve.
Ontario’s 2026 changes include mandatory annual holdback release provisions and transition rules. Have construction counsel confirm the regime, contract dates, notices and release timing that apply. Do not simply assume all holdback remains until the end of a multi-year project.
Align funding with payment obligations. Waiting for a bank draw does not, by itself, suspend obligations under the construction contract or applicable law. Read our construction contract administration guide alongside your adviser’s instructions.
Why draws get delayed
Common pressure points include inconsistent cost reports, undocumented changes, missing permits or insurance records, an unresolved funding shortfall and a request that arrives after the reporting cut-off. Prevent avoidable delay with an agreed checklist and early notice when assumptions change.
Plan working capital for the interval between expenditure and reimbursement. Do not rely on the contractor or suppliers informally financing that gap.
Does a construction loan automatically become a permanent mortgage?
No. Confirm completion, occupancy, leasing and refinancing conditions directly with the lender before relying on take-out funding.
Can this process apply to a renovation?
Yes, depending on the facility and lender. Occupied-building work, deposits and phased handover may need a different reporting structure.
Put construction reporting on a workable footing
FCC’s Construction Management service can help organize budgets, changes and progress information. For plaza-specific preparation, see retail plaza financing. Discuss your scope and reporting needs with FCC; funding decisions remain with lenders and your financial advisers.
Prepared November 18, 2026. Deep Toor, Director of Operations, FCC Builders Canada. General construction-planning information; obtain project-specific lending and legal advice.