Twenty apartments can look straightforward on a concept sketch. The difficult questions usually sit outside the suites: servicing, stairs, parking, approvals and the cash needed before anyone moves in.
For a 10–30 unit rental building, test the site, building concept and financial model together. A unit count is a starting assumption, not proof that the project fits the property or the budget.
First, establish what the land can support
Ask a planner to assess permitted uses, density, height, setbacks and relevant official-plan policies. Review the survey, easements, access, existing agreements and any heritage or environmental constraints. Obtain appropriate geotechnical and environmental advice before relying on a foundation or excavation allowance.
Check water, sanitary, stormwater and electrical capacity with the relevant authorities and utilities. Nearby services do not necessarily mean available capacity or an inexpensive connection. Record off-site work and servicing conditions in the feasibility budget.
Do not treat 10 and 30 units as the same approval case
Site plan requirements depend on the legislation, municipality and property. The Planning Act generally excludes residential development on parcels with no more than 10 units from its definition for site plan control, with exceptions including prescribed areas and land-lease communities. Toronto operates under its own statutory framework.
Ask the municipality to confirm the route for your exact proposal. Exemption from site plan control does not remove zoning, servicing, building-permit or other applicable requirements. A 30-unit project should not be budgeted on the approval assumptions of a 10-unit concept.
Build the right design team early
Coordinate the architect, structural and building-services engineers, civil designer, planner and other required specialists. Have the team establish the applicable code approach, construction type, exits, fire protection, accessibility and energy requirements.
Ask the architect to report both gross building area and rentable area. Corridors, stairs, mechanical rooms and common spaces cost money even though they are not apartment floor area. Repeated suite layouts can simplify coordination, but only if they suit the site and market.
What does a small apartment building cost?
A defensible estimate needs a defined concept, location, structure, servicing scope and finish standard. Avoid multiplying an advertised house-building rate by apartment area. Small buildings still need shared infrastructure, and fixed costs are spread across fewer homes.
Land, acquisition expenses, investigation and demolition.
Site preparation, foundations, structure and envelope.
Suites, common areas, mechanical, electrical and fire protection.
Parking, landscaping, drainage and utility connections.
Design, approvals, development charges and other municipal obligations.
Financing, taxes, insurance, contingency and lease-up costs.
Illustrative feasibility check: if a hypothetical 20-unit project has an all-in budget of $8 million, its average development cost is $400,000 per unit. That is arithmetic, not an Ontario benchmark. Change the suite mix, servicing work or land cost and the result changes. Judge a proposal using a dated, site-specific estimate and rental analysis.
Choose the financing route alongside the design
Ask prospective lenders what equity, appraisal, experience, plans and construction contracts they require. Model the timing of advances and the conditions for permanent financing. Check debt-service assumptions against achievable rents and operating expenses.
Our MLI Select guide explains how potential insurance commitments can influence design. Eligibility is not automatic because a building has enough units. Also review the financing preparation checklist for document organization, adapting it to a rental project rather than a plaza.
Compare concepts before committing to one
For an illustrative site, compare an 18-unit layout with a 24-unit layout. The larger scheme may bring additional rent but also different parking, structure, circulation or approval demands. Ask the team to compare total cost, net rentable area, programme, operating costs and financing assumptions—not just cost per unit.
If a concept depends on uncertain rezoning, servicing capacity or an incentive, show a separate scenario without that assumption. Resolve the decision that could stop the project before spending heavily on finishes.
Sequence delivery through occupancy
Site due diligence and a written feasibility brief.
Concept options, early costing and lender discussions.
Planning approvals and coordinated architectural/engineering design.
Building permits, construction procurement and funding readiness.
Construction, required inspections and cost reporting.
Commissioning, occupancy requirements, deficiencies and operator handover.
Some tasks overlap, but each needs clear dependencies. Use FCC’s construction timeline guide to ask better questions about the critical path.
Does a smaller building mean a simple permit?
Not necessarily. Site constraints, use, building size and design determine the work required. Confirm the approval route early.
Should I buy the site before pricing?
Discuss acquisition conditions with your advisers. Preliminary investigation and concept pricing can reveal issues before an unconditional commitment.
Start with a buildable brief
FCC’s pre-construction and design-build services can help connect a rental concept to scope, costs and sequencing. Share your site, proposed unit count and approval status to discuss the next steps.
Prepared November 18, 2026. Deep Toor, Director of Operations, FCC Builders Canada. General planning information; obtain site-specific professional and financing advice.