Before You Sign the Lease: 12 Unit Checks That Can Prevent Fit-Out Delays

The location works. The rent looks reasonable. You can already picture your business inside.

Before signing, look beyond the floor plan and fresh paint. A leaking roof drain, deteriorated window or unresolved moisture problem can interrupt your fit-out before the first room is finished.

At FCC Builders Canada, issues we often encounter include leaking roof-drain pipes, water penetration around windows, windows requiring replacement, and mould beneath window openings. These conditions deserve attention before you commit to the unit—particularly where repairs depend on the landlord’s contractors, approvals or replacement materials.

The objective is to secure a clear agreement about the condition of the premises, who will correct existing defects and when your contractor can proceed.

First, establish what the landlord is responsible for

Do not assume every existing defect automatically falls to the landlord. Ontario’s commercial-tenancy guidance explains that maintenance responsibilities should be set out in the lease. Have your commercial leasing lawyer review repair, replacement and cost-recovery provisions before signing.

Use the checklist below to identify items to address in the landlord’s work agreement. Distinguish who arranges the repair, who ultimately pays, and who accepts the completed work. Those may be different parties.

1. Leaking roof-drain pipes inside the unit

Look for staining around vertical rainwater pipes, corroded connections, damp ceiling tiles and evidence of previous patching. A pipe carrying roof drainage through your unit can leak even when the roof surface appears sound.

Ask the landlord for the leak history and arrange an inspection by the appropriate trade. Where correction is agreed as landlord work, include investigation, repair and verification—not simply replacement of the stained ceiling tile.

Why it matters: Closing ceilings or installing cabinetry around an unresolved leak can lead to damaged finishes and repeat work.

2. Roof leaks and temporary roof repairs

Ask whether the roof has active leaks, outstanding repairs or a planned replacement. Request available inspection reports and records of recurring problems. A dry viewing on a sunny afternoon may reveal little about what happens during heavy rain or snowmelt.

Have a qualified roofing professional assess concerns; tenants should not access the roof without permission and suitable arrangements.

Before signing: Establish which repairs must be completed before interior work, and how their effectiveness will be checked.

3. Windows that leak or need replacement

Check for water marks, swollen trim, peeling paint, deteriorated frames and moisture at window corners. Fogging between panes can indicate a failed glazing seal, but it does not by itself establish the source of water entering the wall.

Ask for an assessment of whether the problem involves glazing, frames, perimeter seals, flashings or the surrounding wall.

Why it matters: Replacement windows may require fabrication and exterior access. Interior wall finishes around those openings may need to wait.

4. Mould or concealed moisture beneath windows

Fresh paint can hide the visible history of a leak. Look for musty odours, soft drywall, discolouration and damaged baseboards below windows or along exterior walls.

Do not scrape, open or cover suspected affected areas during a casual viewing. Arrange an appropriate assessment and agree on the scope for correcting the moisture source and addressing damaged materials. Ontario’s workplace guidance emphasizes moisture control, cleanup and remediation, with professional assistance for extensive contamination.

Before signing: Avoid accepting “we will paint over it” as the repair plan.

5. Damp floors, water entry and significant slab defects

Inspect floor edges, low points and areas near exterior doors. Ask about previous flooding, recurring dampness, floor movement and substantial cracks.

Your flooring contractor may need moisture testing appropriate to the proposed flooring system. Significant movement or cracking may need engineering assessment.

Why it matters: Flooring installation can be held up while the source is investigated, repairs are completed or the substrate dries. Agree who addresses existing defects and who pays for any additional preparation required by your chosen finish.

6. Existing sanitary drains and plumbing problems

A capped pipe in the floor does not prove that it is usable, correctly located or suitable for your proposed business.

Ask about backups, odours, abandoned connections and previous plumbing repairs. Have a plumber assess relevant existing services and recommend testing or a camera inspection where warranted.

Before signing: Separate correction of defective existing building drainage from new plumbing required for your layout. Confirm access if repairs involve common areas or another tenant’s premises.

7. HVAC equipment that works poorly—or does not suit the space

Ask which equipment serves the unit, its condition, service history and any known faults. Confirm that heating, cooling and controls can be demonstrated under appropriate conditions.

An existing system operating for the previous tenant does not establish that it can support your proposed occupancy or equipment.

Why it matters: Replacements, rooftop access and shared-system shutdowns can affect the programme. Define responsibility for existing equipment repairs separately from upgrades required by your business.

8. Electrical service that has not been properly verified

Do not judge electrical capacity by the size of the panel alone. Have a licensed electrical contractor or electrical consultant verify the available supply, relevant equipment condition and suitability for the intended loads.

Ask whether the landlord has promised a particular service capacity and whether that capacity is actually available to your unit.

Before signing: Resolve responsibility for existing defects, building-side upgrades and tenant distribution. Identify any utility involvement before relying on an opening date.

9. Outstanding fire-protection and life-safety deficiencies

Request available inspection records and information about outstanding deficiencies affecting the unit or shared building systems.

Have the appropriate professionals review concerns involving fire alarms, sprinklers, exit routes, fire-rated doors and separations. A system already installed is not proof that all required work is complete.

Why it matters: Work on shared systems may depend on the landlord’s service contractor and access to other spaces. Separate existing deficiencies from changes triggered by your new layout or use.

For broader approval considerations, see FCC’s commercial renovation and change-of-use guide.

10. Hazardous-material information that is missing

Before planning demolition, request relevant existing hazardous-material surveys and reports, including information about asbestos-containing materials where applicable.

Have a qualified consultant determine whether the available information covers the areas and materials your work will disturb. An old report for another part of the building may not answer the question.

Before signing: Establish responsibility for additional investigation, necessary remediation and its effect on access. Do not assume unidentified materials can be removed as ordinary demolition waste.

11. Exterior doors, entrances and shared access problems

Check for water entering beneath doors, damaged thresholds, doors that do not close properly and deteriorated exterior details. Review the route customers, staff and deliveries will use.

Confirm who maintains shared entrances, corridors and any elevator serving the unit. Ask about planned work or existing faults that could restrict access during construction.

Why it matters: Your interior may be ready while a landlord-controlled entrance or shared access issue still prevents the intended handover.

12. Unfinished landlord work with no firm delivery conditions

“The landlord will take care of it” is not a construction schedule.

Before signing, turn outstanding repairs into a written list with the agreed scope, responsible party, completion date and evidence required for acceptance. Include access for your team to inspect the work before concealing it.

Have your lawyer address how possession, the fixturing period and rent commencement interact with unfinished landlord work, and what happens if agreed deadlines are missed. Do not assume that a delay automatically extends a rent-free period.

Turn the inspection into a landlord work list

For each issue, record:

  • Location and evidence: Marked-up plan, photographs and inspection findings.

  • Agreed repair: The defect to correct and the required finished condition.

  • Responsibility: Who arranges, pays for and checks the work.

  • Deadline: Completion date and the fit-out activities that depend on it.

  • Acceptance: Relevant reports, testing and a joint follow-up inspection.

Arrange any opening-up or intrusive investigation with the landlord’s permission and appropriate professionals. Where an issue cannot be resolved before signing, ask your lawyer how the unresolved risk should be addressed in the agreement.

For allowances, payment arrangements and the broader division of work, read Leasehold Improvements in Ontario: Who Pays, Costs & Lease Checks.

Why a landlord repair can delay your entire fit-out

Consider an illustrative situation: the tenant’s contractor is ready to close a wall, but the window above it still leaks. The landlord must arrange an assessment, approve a repair and potentially order replacement components. The affected wall cannot sensibly be finished until the water-entry problem is resolved and damaged materials are addressed.

That can push back painting, flooring, millwork and equipment installation in the same area. Other work may continue, but repeated visits and changes to the sequence can create additional cost.

Getting the keys does not necessarily mean the unit is ready for uninterrupted construction.

Bring FCC in before you commit to the unit

FCC’s Interior Fit-Outs & Tenant Improvements team can help review visible construction conditions, identify questions for specialist investigation and connect the landlord’s work with your proposed fit-out schedule.

Send us the unit address, intended use, available floor plans and proposed landlord work list. Discuss the space with FCC before signing, while there is still time to resolve the conditions that could delay your opening.

Prepared November 18, 2026. Deep Toor, Director of Operations, FCC Builders Canada.